Question No.271
Which of the following documents describes the details for each component in the WBS?
-
WBS detail
-
Risk register
-
WBS dictionary
-
Project charter
Correct Answer: C
Question No.272
Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?
-
Risk avoidance
-
Risk transference
-
Risk mitigation
-
Risk acceptance
Correct Answer: C
Question No.273
Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?
-
Fallback plan
-
Risk response plan
-
Mitigation management plan
-
Mitigation plan
Correct Answer: A
Question No.274
On which of the following documents you work throughout the risk management processes?
-
Risk management plan
-
Project management plan
-
Risk register
-
Project charter
Correct Answer: C
Question No.275
Small changes that bypass the organization#39;s change control procedures are called .
-
Scope creep
-
Lag
-
Scope fault
-
Gold plating
Correct Answer: A
Question No.276
All of the following information is defined in the program statement of work except for which one?
-
Structure of the program management team
-
Program requirements for resource competency levels
-
Metrics and qualifications for program acceptance
-
Location of the program work
Correct Answer: A
Question No.277
Which of the following documents is described in the statement below?
quot;It is a type of procurement document used to request proposals from prospective sellers of products or services.quot;
-
Request for information
-
Request for quote
-
Request for proposal
-
Request for bid
Correct Answer: C
Question No.278
What does RACI stand for?
-
Responsible, Account, Confirm, Inform
-
Responsible, Accountable, Consult, Inform
-
Roles, Accountable, Confirm, Inform
-
Roles, Action, Consult, Inform
Correct Answer: B
Question No.279
Which of the following is used to build consensus through rounds of anonymous surveys?
-
The Pareto chart
-
The Delphi technique
-
The Monte Carlo simulation
-
The Gantt chart
Correct Answer: B
Question No.280
The quality assurance technique ensures continuous improvement of all processes.
-
Just-in-time management
-
Ishikawa
-
Six Sigma
-
Kaizen
Correct Answer: D