Get Full Version of the Exam
http://www.EnsurePass.com/PMI-ACP.html
Question No.71
The following chart lists stories for a release of an Agile project:
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
A. |
3 |
B. |
4 |
C. |
5 |
D. |
7 |
Correct Answer: B
Question No.72
When interacting with team members, the Agile project manager should:
-
Ask team members to do things by phrasing the statement as a request rather than as a demand.
-
Ignore team member input and emotions when important decisions have to be made.
-
Proceed cautiously when requesting team members to do something likely to make them unhappy.
-
Disagree with the team based on the merit of the issue without considering how the team is feeling.
Correct Answer: A
Question No.73
Which of the following statements is an accurate value statement of the Agile Manifesto?
-
People and places over processes and guidelines
-
Customer collaboration over contract negotiation
-
Working software over complete specifications
-
Managing change over managing a plan
Correct Answer: B
Question No.74
What are three processes used to begin an Agile project?
-
Iterations, Product Road map Planning, and Number of Sprint Iterations
-
Visioning, Product Roadmap Planning, and Product Backlog Definition
-
Visioning, Product Backlog Definition, and Project Charter Creation
-
Burndown chart, Product Roadmap, and sprints#39;length
Correct Answer: B
Question No.75
During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?
-
Denoting development sequence
-
Estimating development hours
-
Indicating priority of a story
-
Estimating points of a story
Correct Answer: C
Question No.76
Which of the following is an example of a visual aid used in Lean-Agile software development?
-
Business value delivered chart
-
Product technical specifications
-
Automated code coverage report
-
Scrum-of-Scrum report
Correct Answer: A
Question No.77
A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process.The project manager#39;s initial plan should be to:
-
Institute daily standup meetings immediately.
-
Communicate the Agile Manifesto to the team.
-
Balance teaching principles with Agile practices.
-
Rate the team#39;s progress in learning new methods.
Correct Answer: C
Question No.78
A technique showing Kanban work stages by comparing counted features over a time interval is called a/an:
-
Earned value system.
-
Fully integrated backlog.
-
Cumulative flow diagram.
-
Progressive elaboration.
Correct Answer: C
Question No.79
Which is the best option to improve project velocity?
-
Shield programmers from interruptions
-
Minimize customer involvement
-
Shorten the iteration length
-
Increase project team size
Correct Answer: A
Question No.80
In the Lean process, the focus is on:
-
Managing team efficiency.
-
Optimizing completed work across the process stream.
-
Using the optimal resources.
-
Cross training the team to eliminate bottlenecks.
Correct Answer: B